Total Requests (2026)
334
100% of records
●
Total Value (YTD)
RM 129.6M
▼ 11.0% vs 2025
●
Avg Cycle Time
49.3 Days
▲ 1.5% vs 2025
●
Completed
32.9%
110 of 334

Request Status (YTD)

334 Total
Completed (110) In Evaluation (85) Pending Approval (79) Cancelled (32) PO Issued (28)

Pipeline Overview

32.9% Completed
Completed 32.9% On-Time Delivery 22.8% Delayed 53.6%

SLA Compliance

46.4% Within SLA
Within SLA 155 Beyond SLA 179 Method compliance 100%

KPI Within SLA: 89.5% vs target 85% (Green)

Value by Category (RM Million)

Procurement Method Mix

Average Cycle Days by PTJ

Overall average 49.3 days

Monthly Trend (Volume & Value)

Top Delayed Procurements

ID PTJ Category Amount (RM) Cycle SLA Overrun Risk
PR-2026-00611 Faculty of Computing Office Supplies 1,477,141 140d 90d +50d High
PR-2026-00235 Malaysia-Japan International Institute of Technology Equipment 492,659 127d 90d +37d High
PR-2026-00520 School of Graduate Studies ICT 1,651,919 125d 90d +35d Medium
PR-2026-01124 Corporate Affairs Department Laboratory 598,888 125d 90d +35d Medium
PR-2026-00454 Registrar's Office ICT 961,072 124d 90d +34d Medium
PR-2026-00815 Faculty of Social Sciences & Humanities Facilities 1,312,456 124d 90d +34d Medium
PR-2026-00293 Razak Faculty of Technology & Informatics Equipment 1,738,911 121d 90d +31d Medium
PR-2026-00975 Development & Asset Management Department Professional Services 837,952 121d 90d +31d Medium

Risk Profile

334 Requests
Low 155 Medium 156 High 23

Open Alerts

  • High — Procurement cycle delay (Development & Asset Management Department)
  • Medium — Procurement monitoring alert (Faculty of Management)
AI

AI Executive Summary

  • Average procurement cycle is 49.3 days (slower vs 2025).
  • 179 of 334 requests (53.6%) are delayed beyond SLA; 23 flagged as high risk.
  • 32.9% completed · method compliance at 100%.